Goderich Watermain & Storm
Goderich Watermain & Storm Sewer Replacement
From Forsythe Street to Princess Street
Budget:
$457,000
Construction Timeline:
- Start of Construction - Spring 2019
- End of Construction - Summer 2019
Notice to Residents:
- July 12, 2018 - Notice of PIC
- January 15, 2019 - Notice of Construction