Wintemute St Sanitary Sewer Repl.
Wintemute Street Sanitary Sewer Replacement
110m West of Central Avenue to Niagara Parkway
Budget:
$440,000
Construction Timeline:
- Phase 1
- Start of Construction - Fall 2018
- End of Construction - February 2019
- Phase 2
- TBD
Notice to Residents:
- January 2019 - Notice of Temporary Disruption to Sanitary Sewer Services
- January 2019 - Notice to Residents
Contact Information for the Project:
Town Contact:
- Robert D. Judd, P.Eng., Municipal Engineer - Infrastructure Renewal, Engineering Division, rjudd@forterie.ca, 905-871-1600, ext. 2412
Constultant
- Robinson Construction
- Kevin Bainbridge, 905-304-0080 ext. 222, kbainbridge@rcii.com
Contractor
- Phase 1
- PipeFlo
- Phase 2
- TBD